Projects Metrics Report

The Monitor Process includes a Projects Metrics report task. The Projects Metrics report displays various project statistics.

For a description of this calculation, see Monitoring Reports (Overview).

The following table describes the fields that are displayed in this report:

Field

Description

Cost Variance

Budgeted Cost of Work Performed - Actual Cost of Work Performed

Schedule Variance

Budgeted Cost of Work Performed - Budgeted Cost for Work Scheduled

Budget Remaining

Total Budget - Actual Cost of Work Performed

Budgeted Cost of Work Remaining

Total Budget - Budgeted Cost of Work Performed

Cost Performance Index

Budgeted Cost of Work Performed/Actual Cost of Work Performed; >1 indicates costs are under budget; <1 indicates costs are over budget

Schedule Performance Index

Budgeted Cost of Work Performed/Budgeted Cost for Work Scheduled; >1 indicates ahead of schedule; <1 indicates behind schedule

% Complete by Budget

100 * (Budgeted Cost of Work Performed/Total Budget)

% Budget Spent

100 * (Actual Cost of Work Performed/Total Budget)

Owner Changes

Total actual costs for all change order actions initiated by the owner.

Vendor Changes

Total actual costs for all change order actions initiated by the vendor.