The Monitor process includes a Projects Calendar task. This report is a View Analysis view. If you click on an item in the calendar, a detail view is displayed for the project, work package, or action you selected.
The Projects Calendar varies based on the criteria that you specify.
To display a projects calendar:
Note: In order to display work packages, you must first specify a Project Name in the console.
The calendar displays the items that meet your restriction.
Note: The number of days of the week that are displayed as work days is based on the Days Per Week value that you specified for a project or work package. For example, if you specified 5 days as the project/work package Days Per Week value, Monday-Friday are displayed as work days. Holidays are not displayed.
Copyright © 1984-2014, ARCHIBUS, Inc. All rights reserved. |