Capital Project Management / Project Management / Monitor

Projects Analysis Report

The Monitor process includes a Projects Analysis report. The Projects Analysis report displays various project statistics. This report depends on having up-to-date Action Item Status entered for your work package action items.

The following table describes the fields that are displayed in this report:

Field

Description

Total Estimated Costs

Total estimated design costs

Total Actual Costs

Total actual costs

Variance

Variance between the estimated design costs and actual costs

% Variance

The % variance between the estimated design costs and actual costs

% Complete Design

The % of completed project actions in the Design Project Phase (Project Status of Approved or Approved - In Design).

% Complete Execution

The % of completed project actions in the Execution Project Phase (Project Status of Issued-In Progress or Issued On-Hold.).

% Complete Total

The % complete of all of the project's actions.