Capital Project Management / Project Management/ Plan
Capital Project Management / Commissioning / Design

Estimate Design Costs

To estimate design costs, you first enter or edit these costs for each action item within a project. The program then rolls up all of your action costs for the entire project.

For information on adding costs to actions, see Adding and Editing Actions.

You can estimate design costs from the Management or Commissioning Consoles or from the Process Navigator task. The procedure describes how to access the view in both these ways.

To estimate design costs for a project:

  1. Do one of the following:
  2. To adjust costs:
    1. In the Adjust Costs panel, click Adjust for the action whose costs you want to change.

      The Edit Estimated Costs for Action Items dialog appears.

    2. Enter or modify values in the Cost-Est. Baseline (Cap.) and Cost-Est. Baseline (Exp.) fields, and click Save.
  3. To export the data to Excel, click XLS.
  4. To generate a paginated report of the action item costs, click DOC.
Copyright © 1984-2014, ARCHIBUS, Inc. All rights reserved.